  • Apr 27
  • 2 min read

Updated: Apr 28

May 2026

In progress:

  • Finish basement washrooms

  • Paint newly installed basement walls

  • Prepare for the Annual General Meeting

  • Install elevator/lift


Future:

Basement:

  • Seal the stone foundation walls (as needed)


Main floor:

  • Repair the northern exterior windows

  • Insulate and finish the front entrance

  • Replace the floor in the northeast room

  • Repair the plaster on the walls and ceiling

  • Restore the dome

  • Wire in electricity

  • Install lighting and signage

  • Install hardwood flooring

  • Source and install furnishings


April 2026

Basement:

  • Drywall accessible washrooms

  • Install fire-rated doors

  • Plan the inaugural Annual General Meeting


March 2026

Basement:

  • Insulate and drywall stairways

  • Fundraise

  • Adopt initial bylaws

  • Plan the inaugural membership program


February 2026

Basement:

  • Frame accessible basement washrooms

  • Purchase tables and chairs for basement

  • Apply for grants


January 2026

Basement:

  • Replace the windows in the north room

  • Install emergency and exit lights

December 2025

  • Insulate the two basement entrances

  • Refinish the basement floor


November 2025

  • Connect to municipal water

  • Install the automatic bell ringer

  • Grind and paint the floor and knee walls

  • Host Hometown for the Holidays event on November 29


October 2025:

  • Connect the new furnaces to the existing ductwork

  • Restore original internal north room windows

  • Grant writing and fundraising

  • Plan winter events

  • Enlist a Volunteer Coordinator

  • Establish subcommittees (Construction, Events, Decorating, Fundraising, Media)


September 2025:

  • Successful Open House on September 14!

  • Expose original wainscotting


August 2025:

  • Attended the Comber Fair!

  • Removal of chimney

  • Refinish wood around front entry

  • Design basement ramps


July 2025:

  • Bell tower windows closed up

  • East, West and North windows repaired and sealed


June 2025:

  • Hardwood flooring purchased for the sanctuary

  • Flower beds were renewed and planted

  • Landscaping behind building has been refreshed

  • Exterior restoration ongoing

  • Basement lighting installed


May 2025:

  • Ductwork cleaned

  • New electrical panel installed

  • New furnace installed

  • New sump pump installed

  • Connected to hydro

  • Professional mold remediation


April 2025:

  • The front door's broken glass was repaired and secured

  • Flooring has been repaired or replaced where needed 

  • Unsecured plaster was repaired and necessary drywall was removed

  • The entire building’s main floor and basement were cleaned

  • Side entrance roofs were replaced


November 2024:

Initial Assessment - Complete

  • Basement pumped and cleaned

  • Front window reinstalled

  • Initial main floor and orchestra cleaning

  • Building purchased by 927 St. Joachim L'Association

 
 
 

2 Comments


Al
May 11

Great work, thanks for sharing detailed updates each month!

Like

Paul Sylvestre
Oct 14, 2025

Je suis né à Saint-Joachim le 30 décembre 1947. Je suis très heureux d'apprendre que l'église de mon village natale est en train d'être rénovée pour en faire un vivrant centre d'activités communautaires.

Like
bottom of page