What's going on right now?
- Feb 10
- 2 min read
February 2026
In Progress:
Basement:
Install accessible basement washrooms
Install fire-rated doors
Purchase tables and chairs for basement
Apply for grants
Future:
Basement:
Seal the stone foundation walls
Main floor:
Install basement ramps / elevator
Repair the large exterior windows on the north of the building
Insulate and drywall the front entrance
Replace the floor in the northeast room
Repair the plaster on the walls and ceiling
Restore the dome
Wire in electricity
Install acessible washrooms
Install lighting and signage
Install hardwood flooring
Source and install furnishings
January 2026
Basement:
Replace the windows in the north room
Install emergency and exit lights
December 2025
Insulate the two basement entrances
Refinish the basement floor
November 2025
Connect to municipal water
Install the automatic bell ringer
Grind and paint the floor and knee walls
Host Hometown for the Holidays event on November 29
October 2025:
Connect the new furnaces to the existing ductwork
Restore original internal north room windows
Grant writing and fundraising
Plan winter events
Enlist a Volunteer Coordinator
Establish subcommittees (Construction, Events, Decorating, Fundraising, Media)
September 2025:
Successful Open House on September 14!
Expose original wainscotting
August 2025:
Attended the Comber Fair!
Removal of chimney
Refinish wood around front entry
Design basement ramps
July 2025:
Bell tower windows closed up
East, West and North windows repaired and sealed
June 2025:
Hardwood flooring purchased for the sanctuary
Flower beds were renewed and planted
Landscaping behind building has been refreshed
Exterior restoration ongoing
Basement lighting installed
May 2025:
Ductwork cleaned
New electrical panel installed
New furnace installed
New sump pump installed
Connected to hydro
Professional mold remediation
April 2025:
The front door's broken glass was repaired and secured
Flooring has been repaired or replaced where neededÂ
Unsecured plaster was repaired and necessary drywall was removed
The entire building’s main floor and basement were cleaned
Side entrance roofs were replaced
November 2024:
Initial Assessment - Complete
Basement pumped and cleaned
Front window reinstalled
Initial main floor and orchestra cleaning
Building purchased by 927 St. Joachim L'Association